DP Ruto in panic after 106 million Nyeri stadium funds go missing

Nyeri MP ngunjiri wambugu

By Ngunjiri Wambugu vai fb

During Jubilee manifesto launch in 2017 the deputy president said that Ruringu stadium in Nyeri would be complete in a couple of months but there is something shocking, that stadium is in a mess, no work so far, millions embezzled.

106M SPENT IN RURING’U STADIUM?
WHERE? GROUND NI DIFFERENT!!!

Yesterday I toured Ruringu Stadium. I wanted to see where the 106M which is indicated as work done in the stadium so far, has gone.

The 106M is 20M that was paid at inception of the contract. 44M that has been paid via certificates. And 42M that’s pending worth of unpaid certificates].

106M is also 33% of the 320M needed to build our stadium. This means that on the ground we should see close to one third worth of work required.

But in the literal sense,

GROUND NI DIFFERENT … SANA!!!

There is absolutely nothing to see on the ground. NOTHING! (The perimeter wall you see was constructed by the County Government).

This is unacceptable. In coming days I will want to understand who was paid this money, and what they say they did with it. I also want to know why the stadium has stalled despite being launched by The President HE Uhuru Kenyatta over 3 years ago.

#Kitaeleweka

What do you think?

Written by Mighty Diamond

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

Loading…

0

DP Ruto should apologize for looting Kenya, should stop witch hunting ODM

Tanga tanga wing ashamed our party in Kibra, desperate for power- Hon Ngunjiri